The objective of this project is To provide commercially viable continuous supply of electricity for house-hold use in rural area of the state while restricting supply for agricultural use to facilitate only sustainable exploitation of ground water.
Thereby, to accelerate socio economic development of rural area and pursue the larger objective of sustainable ‘inclusive growth’.
Project Highlights
Highlights of FSP
A total amount of Rs 1,778 Crore will be spent on the feeder separation project funded by Rural Electrification Corporation and Asian Development Bank (ADB). The project includes separation of 1645 no 11kV rural feeder of 17 districts benefiting 15860 villages.
Lot wise Status
Lot wise status in a dashbord format are available in this section.
Targets for the Month
During the month, 125 new feeders were surveyed & 30 new BOQ’s has been finalized. Execution work is being carried out in six divisions.
Location of the Month
This section highlights location (lot no) with maximum progress as compared to other locations, in a particlar month.
Site Photos